NESTLE UPGRADE OF CLOAKROOM
No 38 Light house Street, Agbara, Ogun
Project Description:
This project involves upgrading the cloak room for employees
Project Start:
17.11.2025
Expected End
30.11.2025
Report Week
Week 2
Site Preparation
61%
Foundation Work
57%
Framing Activities
32%
OVERALL PROJECT COMPLETION
38%
Project in Pictures
Indoor
Outdoor
Sitting Room
Kitchen
Progress Report
Work Completed This Week:
Site Preparation
Completed the grading and leveling of the site.
Excavation for the foundation was finalized.
Removed debris and ensured the site is clear for construction activities.
Foundation Work
Poured concrete for the footings and allowed proper curing.
Installed rebar reinforcements for added structural integrity.
Began forming the foundation walls.
Framing Activities
Delivered and inspected framing materials.
Started framing the ground floor walls and marked layout for interior partitions.
Installed temporary supports to ensure alignment.
UPCOMING ACTIVITIES
Upcoming Activities for Next Week:
Foundation Work
Complete curing of foundation walls and conduct structural integrity inspections.
Backfill around the foundation to ensure proper drainage and stability.
Framing
Continue framing for the upper floors, including walls and floor joists.
Install beams and supports for the roof structure.
Begin framing interior walls and partitions.
Prepared By:
Emmanuel Efe Asika
Project Manager
Date Prepared:
25/11/2025