NESTLE UPGRADE OF CLOAKROOM
No 38 Light house Street, Agbara, Ogun
Project Description:
This project involves upgrading the cloak room for employees
Project Start:
01.10.2025
Expected End
01.12.2025
Report Week
Week 2
Task 1
3%
Task 2
30%
Task 3
5%
Task 4
40%
Task 5
20%
Task 6
6%
6%
Task 7
10%
Task 8
20%
OVERALL PROJECT COMPLETION
17%
Project in Pictures
Indoor
Outdoor
Sitting Room
Kitchen
Progress Report
Work Completed This Week:
1. Site Preparation:
Completed the grading and leveling of the site.
Excavation for the foundation was finalized.
Removed debris and ensured the site is clear for construction activities.
2. Foundation Work:
Poured concrete for the footings and allowed proper curing.
Installed rebar reinforcements for added structural integrity.
Began forming the foundation walls.
3. Framing Activities:
Delivered and inspected framing materials.
Started framing the ground floor walls and marked layout for interior partitions.
Installed temporary supports to ensure alignment.
4. Plumbing and Electrical Preparations:
Laid underground plumbing pipes and inspected for leaks.
Installed electrical conduits in preparation for wiring.
Conducted pre-inspections to ensure compliance with local codes.
UPCOMING ACTIVITIES
Upcoming Activities for Next Week:
1. Foundation Work:
Complete curing of foundation walls and conduct structural integrity inspections.
Backfill around the foundation to ensure proper drainage and stability.
2. Framing:
Continue framing for the upper floors, including walls and floor joists.
Install beams and supports for the roof structure.
Begin framing interior walls and partitions.
3. Roofing:
Deliver and stage roofing materials on-site.
Begin installation of roof trusses and sheathing.
Prepare for waterproofing and weatherproofing of the roof.
Prepared By:
Michael Odey
Project Manager
Date:
15.11.2025